University of New South Wales Chemical Science

   
Overview
CONSTRUCTION VALUE:

$2.50 million

PROGRAMME DURATION:

11 weeks

DESCRIPTION:

The F10 Mezzanine refurbishment involved the complete demolition of approximately 1000m2 of existing lecture theatres and teaching facilities..

KEY CHALLENGES:
  1. Working in an operational premises
  2. Working alongside students
  3. Removal of friable asbestos
  4. Removal and upgrade of services without disrupting existing facilities
PROJECT SUCCESSES:

Delivery within client timeframe to a very high standard with minimal disruption to other occupants.

Services

Project details
  • Client: UNSW Chemical Science, Kensington Campus Sydney